2015: | Single phase no. 1 | |
Schedule: 01.10.2015 - 18.12.2015 | ||
Objectives: | System structure achievement |
2016: | Single phase no. 2 | |
Schedule: 19.12.2015 - 16.12.2016 | ||
Objectives: | System’s automatic control algorithms achievement (with preliminary validation) | |
Electromechanical wind turbine simulator implementation | ||
Pv simulator implementation | ||
Build of the bidirectional converter for energy flow management to/from batteries | ||
Working/training visit |
2017: | Single phase no. 3 | |
Schedule: 17.12.2016 - 30.09.2017 | ||
Objectives: | Build of the bidirectional converter for energy flow management to/from grid | |
Grid distributed systems for generating and using electrical energy (GDSGUEE) development system implementation | ||
Working/training visit | ||
Experimental validation of the structure and control algorithms for GDSGUEE |